CTFL-AT - 1. Agile Software Development - 1.2. Aspects of Agile Approaches (Part 1/2)

UDECAREER21/06/2024~8 phút đọc

There are a number of Agile approaches in use by organizations. Common practices across most Agile organizations include collaborative user story creation, retrospectives, continuous integration, and planning for each iteration as well as for overall release. This subsection describes some of the Agile approaches. 

1.2.1 Agile Software Development Approaches 

There are several Agile approaches, each of which implements the values and principles of the Agile Manifesto in different ways. In this syllabus, three representatives of Agile approaches are considered: Extreme Programming (XP), Scrum, and Kanban. 

Extreme Programming 

Extreme Programming (XP), originally introduced by Kent Beck [Beck04], is an Agile approach to software development described by certain values, principles, and development practices. 

XP embraces five values to guide development: communication, simplicity, feedback, courage, and respect. 

XP describes a set of principles as additional guidelines: humanity, economics, mutual benefit, selfsimilarity, improvement, diversity, reflection, flow, opportunity, redundancy, failure, quality, baby steps, and accepted responsibility.

XP describes thirteen primary practices: sit together, whole team, informative workspace, energized work, pair programming, stories, weekly cycle, quarterly cycle, slack, ten-minute build, continuous integration, test first programming, and incremental design. 

Many of the Agile software development approaches in use today are influenced by XP and its values and principles. For example, Agile teams following Scrum often incorporate XP practices. 

Scrum 

Scrum is an Agile management framework which contains the following constituent instruments and practices [Schwaber01]: 

  • Sprint: Scrum divides a project into iterations (called sprints) of fixed length (usually two to four weeks).
  • Product Increment: Each sprint results in a potentially releasable/shippable product (called an increment). 
  • Product Backlog: The product owner manages a prioritized list of planned product items (called the product backlog). The product backlog evolves from sprint to sprint (called backlog refinement). 
  • Sprint Backlog: At the start of each sprint, the Scrum team selects a set of highest priority items (called the sprint backlog) from the product backlog. Since the Scrum team, not the product owner, selects the items to be realized within the sprint, the selection is referred to as being on the pull principle rather than the push principle. 
  • Definition of Done: To make sure that there is a potentially releasable product at each sprint’s end, the Scrum team discusses and defines appropriate criteria for sprint completion. The discussion deepens the team’s understanding of the backlog items and the product requirements.
  • Timeboxing: Only those tasks, requirements, or features that the team expects to finish within the sprint are part of the sprint backlog. If the development team cannot finish a task within a sprint, the associated product features are removed from the sprint and the task is moved back into the product backlog. Timeboxing applies not only to tasks, but in other situations (e.g., enforcing meeting start and end times). 
  • Transparency: The development team reports and updates sprint status on a daily basis at a meeting called the daily scrum. This makes the content and progress of the current sprint, including test results, visible to the team, management, and all interested parties. For example, the development team can show sprint status on a whiteboard.

Scrum defines three roles: 

  • Scrum Master: ensures that Scrum practices and rules are implemented and followed, and resolves any violations, resource issues, or other impediments that could prevent the team from following the practices and rules. This person is not the team lead, but a coach. 
  • Product Owner: represents the customer, and generates, maintains, and prioritizes the product backlog. This person is not the team lead. 
  • Development Team: develop and test the product. The team is self-organized: There is no team lead, so the team makes the decisions. The team is also cross-functional (see Section 2.3.2 and Section 3.1.4). 

Scrum (as opposed to XP) does not dictate specific software development techniques (e.g., test first programming). In addition, Scrum does not provide guidance on how testing has to be done in a Scrum project. 

Kanban 

Kanban [Anderson13] is a management approach that is sometimes used in Agile projects. The general objective is to visualize and optimize the flow of work within a value-added chain. Kanban utilizes three instruments [Linz14]:

  • Kanban Board: The value chain to be managed is visualized by a Kanban board. Each column shows a station, which is a set of related activities, e.g., development or testing. The items to be produced or tasks to be processed are symbolized by tickets moving from left to right across the board through the stations. 
  • Work-in-Progress Limit: The amount of parallel active tasks is strictly limited. This is controlled by the maximum number of tickets allowed for a station and/or globally for the board. Whenever a station has free capacity, the worker pulls a ticket from the predecessor station. 
  • Lead Time: Kanban is used to optimize the continuous flow of tasks by minimizing the (average) lead time for the complete value stream.

Kanban features some similarities to Scrum. In both frameworks, visualizing the active tasks (e.g., on a public whiteboard) provides transparency of content and progress of tasks. Tasks not yet scheduled are waiting in a backlog and moved onto the Kanban board as soon as there is new space (production capacity) available. 

Iterations or sprints are optional in Kanban. The Kanban process allows releasing its deliverables item by item, rather than as part of a release. Timeboxing as a synchronizing mechanism, therefore, is optional, unlike in Scrum, which synchronizes all tasks within a sprint.

1.2.2 Collaborative User Story Creation 

Poor specifications are often a major reason for project failure. Specification problems can result from the users’ lack of insight into their true needs, absence of a global vision for the system, redundant or contradictory features, and other miscommunications. In Agile development, user stories are written to capture requirements from the perspectives of developers, testers, and business representatives. In sequential development, this shared vision of a feature is accomplished through formal reviews after requirements are written; in Agile development, this shared vision is accomplished through frequent informal reviews while the requirements are being written. 

The user stories must address both functional and non-functional characteristics. Each story includes acceptance criteria for these characteristics. These criteria should be defined in collaboration between business representatives, developers, and testers. They provide developers and testers with an extended vision of the feature that business representatives will validate. An Agile team considers a task finished when a set of acceptance criteria have been satisfied. 

Typically, the tester’s unique perspective will improve the user story by identifying missing details or non-functional requirements. A tester can contribute by asking business representatives open-ended questions about the user story, proposing ways to test the user story, and confirming the acceptance criteria. The collaborative authorship of the user story can use techniques such as brainstorming and mind mapping. The tester may use the INVEST technique [INVEST]: 

  • Independent 
  • Negotiable
  • Valuable 
  • Estimable 
  • Small 
  • Testable 

According to the 3C concept [Jeffries00], a user story is the conjunction of three elements: 

  • Card: The card is the physical media describing a user story. It identifies the requirement, its criticality, expected development and test duration, and the acceptance criteria for that story. The description has to be accurate, as it will be used in the product backlog.
  • Conversation: The conversation explains how the software will be used. The conversation can be documented or verbal. Testers, having a different point of view than developers and business representatives [ISTQB_FL_SYL], bring valuable input to the exchange of thoughts, opinions, and experiences. Conversation begins during the release-planning phase and continues when the story is scheduled. 
  • Confirmation: The acceptance criteria, discussed in the conversation, are used to confirm that the story is done. These acceptance criteria may span multiple user stories. Both positive and negative tests should be used to cover the criteria. During confirmation, various participants play the role of a tester. These can include developers as well as specialists focused on performance, security, interoperability, and other quality characteristics. To confirm a story as done, the defined acceptance criteria should be tested and shown to be satisfied. 

Agile teams vary in terms of how they document user stories. Regardless of the approach taken to document user stories, documentation should be concise, sufficient, and necessary. 

1.2.3 Retrospectives 

In Agile development, a retrospective is a meeting held at the end of each iteration to discuss what was successful, what could be improved, and how to incorporate the improvements and retain the successes in future iterations. Retrospectives cover topics such as the process, people, organizations, relationships, and tools. Regularly conducted retrospective meetings, when appropriate follow up activities occur, are critical to self-organization and continual improvement of development and testing. 

Retrospectives can result in test-related improvement decisions focused on test effectiveness, test productivity, test case quality, and team satisfaction. They may also address the testability of the applications, user stories, features, or system interfaces. Root cause analysis of defects can drive testing and development improvements. In general, teams should implement only a few improvements per iteration. This allows for continuous improvement at a sustained pace. 

The timing and organization of the retrospective depends on the particular Agile method followed. Business representatives and the team attend each retrospective as participants while the facilitator organizes and runs the meeting. In some cases, the teams may invite other participants to the meeting. 

Testers should play an important role in the retrospectives. Testers are part of the team and bring their unique perspective [ISTQB_FL_SYL], Section 1.5. Testing occurs in each sprint and vitally contributes to success. All team members, testers and non-testers, can provide input on both testing and non-testing activities. 

Retrospectives must occur within a professional environment characterized by mutual trust. The attributes of a successful retrospective are the same as those for any other review as is discussed in the Foundation Level syllabus [ISTQB_FL_SYL], Section 3.2.

Tiếp tục hành trình học tập cùng UDECAREER

Khám phá các Learning Paths, lựa chọn khóa học phù hợp và bắt đầu với những kỹ năng bạn cần cho giai đoạn hiện tại.

Truy cập UDECAREER Learninghttps://learning.udecareer.com ↗
Mã QR UDECAREER Learning
Quét mã QRđể truy cập UDECAREER Learning trên thiết bị di động.
Đầu trang